APR/AC-LIGHT DUTY PRIMER

Go back to product info

Preparation

  • primer/nylon roller
  • drill with mixing spindle attachment
  • gloves

Mixing

  • Measure the moisture content of the substrate: max 5%
  • make sure the floor is free of dust and grease and that any loose particles have been removed
  • tape the edges to a sufficient height to prevent splashes
  • check you have sufficient material (for consumption, see label)

Application: scatter

  • Application: Pour the mixture onto the floor and spread evenly with a primer/nylon roller, or a brush
      • Note: If the primer application is too thick, the curing will take longer!
  • Remove

Application: remove excess sand

because this primer is applied very thinly, it is best to scatter with 0.1-0.3 mm fire-dried sand

Cleaning tools

after drying (+/- 1-2 hrs at 20°C) the excess sand

Additional points of attention

  • Used rolls cannot be reused.
  • Empty packaging: cured material or scrapings => construction waste, otherwise => chemical waste
  • Cleaning mixing spindle attachment with water or acetone

Disclaimer

  • Note: wait to apply the next layer until this layer has become completely transparent
  • Note: If the primer application is too thick, the curing will take longer!
  • Note: Not suitable under vapour-tight finishing layers
  • Note: Not suitable for use in wet rooms

Video

Disclaimer

These brief installation instructions are provided to help you quickly get started with the installation. However, it is important to first read the technical data sheet and to take note of the safety data sheets Both documents can be found at the bottom of this page under downloads.